* '''Timeline:'''
* '''Timeline:'''
** '''Detailed Schedule:''' [https://docs.google.com/spreadsheet/ccc?key=0AopkixSrywUIdE5aMngyYk53bEkxd2FtYUthS2hjbXc&usp=sharing]
** '''Detailed Schedule:''' [https://docs.google.com/spreadsheet/ccc?key=0AopkixSrywUIdE5aMngyYk53bEkxd2FtYUthS2hjbXc&usp=sharing]
**Week 0 (May 19 to May 26):
**Week 0 (May 19 to May 26): Complete the implementation, tests and documentation for 3D Coordinate systems functions.  
Complete the implementation, tests and documentation for 3D Coordinate systems functions.  
**Week 1 to Week 4 (May 27 to June 25): Complete the implementation, testing and documentation of missing functions in Modelling the Earth group in Week 1 and Week 2 and also the selected missing functions in Geographic Coordinate Systems group in Week 3 and Week 4. Submit the following functions for mid term evaluation.1. Modelling the Earth functions ,2. Selected functions in Geographic Coordinate systems ,3. 3D Coordinate system
**Week 1 to Week 4 (May 27 to June 25):
**Week 5 to Week 7 (June 26 to July 14): Complete the implementation,tests and documentation of the following functions 1. Remaining functions in Geographic Coordinate Systems group by the end of Week 5 ,2. Lengths and Angles group by Week 6, Small Circles, Ellipses ,3. Spherical Distance group by the end of Week 7
Complete the implementation, testing and documentation of missing functions in Modelling the Earth group in Week 1 and Week 2 and also the selected missing functions in Geographic Coordinate Systems group in Week 3 and Week 4. Submit the following functions for mid term evaluation.
**Week 8 to Week 10 (July 15 to August 5): Complete the implementation,tests and documentation of missing functions in Great Circles, Geodesics, and Rhumb Lines by the end of Week 10.
1. Modelling the Earth functions  
**Week 11 to Week 12 (August 6 to August 18): This is a buffer time of two weeks to accommodate for any unpredictable delay. Refine tests and documentation for whole project. Code clean up and finalization. End of GSOC.
2. Selected functions in Geographic Coordinate systems
**After GSOC: Maintenance and further development of Mapping Package in Octave Forge.
3. 3D Coordinate system
**Week 5 to Week 7 (June 26 to July 14):
Complete the implementation,tests and documentation of the following functions
1. Remaining functions in Geographic Coordinate Systems group by the end of Week 5
2. Lengths and Angles group by Week 6, Small Circles, Ellipses
3. Spherical Distance group by the end of Week 7.
**Week 8 to Week 10 (July 15 to August 5):
Complete the implementation,tests and documentation of missing functions in Great Circles, Geodesics, and Rhumb Lines by the end of Week 10.
**Week 11 to Week 12 (August 6 to August 18):
This is a buffer time of two weeks to accommodate for any unpredictable delay. Refine tests and documentation for whole project. Code clean up and finalization.
End of GSOC.
**After GSOC:
Maintenance and further development of Mapping Package in Octave Forge.
   
   
I have planned for a 40 hour work schedule every week.  
I have planned for a 40 hour work schedule every week.  