* I have selected the following task from GSoC projects page[http://wiki.octave.org/Summer_of_Code_Project_Ideas].
** I would like to implement the functions for Coordinate systems, Geodesy and Projections for Mapping Package in Octave Forge. The list of missing functions in the mapping package are grouped here [https://docs.google.com/spreadsheet/ccc?key=0AopkixSrywUIdEpaWVktM3hUQjBWZEZVTnlPRFJfU0E&usp=sharing]. The details of the functions that I have proposed to implement are present in the detailed schedule below. I have already contributed the 3D coordinate functions to this end[https://savannah.gnu.org/patch/index.php?8377].
* '''Rough time estimatesTimeline:'''
** '''Detailed Schedule:''' [https://docs.google.com/spreadsheet/ccc?key=0AopkixSrywUIdE5aMngyYk53bEkxd2FtYUthS2hjbXc&usp=sharing]
** Week 0 (May 19 to May 26): Familiarizing with Octave code. Complete the implementation, tests and documentation for 3D Coordinate system systems functions that I have already implemented. ** Week 1 to Week 4 (May 27 to June 25): Complete the implementation , testing and documentation of missing functions in Modelling the Earth group in Week 1 and Week 2 and also certain the selected missing functions in Geographic Coordinate Systems groupin Week 3 and Week 4. Complete Submit the tests and submit following functions for mid term evaluation.1. Modelling the Earth functions, 2. Certain Selected functions in Geographic Coordinate systems, 3. 3D Coordinate system functions for mid term evaluation. ** Week 5 to Week 7 (June 26 to July 14): Complete the implementation ,tests and testing documentation of missing the following functions1. Remaining functions remaining in Geographic Coordinate Systems group by the end of Week 5, 2. Lengths and Angles group by Week 6, Small Circles, Ellipses, and 3. Spherical Distance group by the end of Week 7.** Week 8 to Week 10 (July 15 to August 5): Complete the implementation ,tests and testing documentation of missing functions in Great Circles, Geodesics, and Rhumb Lines by the end of Week 10. ** By Week 11 to Week 12 (By August 6 to August 18): Fix This is a buffer time of two weeks to accommodate for any remaining bugs or Compatibility issuesunpredictable delay. Write remaining Refine tests and Documentationdocumentation for whole project. Code clean up and finalization. End of GSOC. ** After GSOC: Maintenance and further development of Mapping Package in Octave Forge. I have planned for a 40 hour work schedule every week. I will be unavailable for 4 days during the entire GSOC period due to personal commitments.
A Buffer Further details of two weeks(Week 11, Week 12) has been kept for any unpredictable delay.I have planned a 40 hour work my schedule for every week. I will be unavailable for 4 days during the entire GSoC period due to personal commitmentsGSOC are present at this link.