Line 47: | Line 47: | ||
** Do you like to code a proof of concept to 'see how it turns out', modifying that and taking the risk of having work thrown away if it doesn't match what the project or original proponent had in mind?(NO) | ** Do you like to code a proof of concept to 'see how it turns out', modifying that and taking the risk of having work thrown away if it doesn't match what the project or original proponent had in mind?(NO) | ||
== Y: Your task == | == Y: Your task == | ||
* I have selected | * I have selected the following task from GSoC projects page[http://wiki.octave.org/Summer_of_Code_Project_Ideas]. | ||
** I would like to contribute to the mapping package, specifically the implementations of functions missing in Coordinates, Geodesy, Projections and Standard I/O. The list of functions in the map toolbox for Matlab are listed here[http://www.mathworks.in/help/map/functionlist.html]. I have already contributed the 3D coordinate functions to this package[https://savannah.gnu.org/patch/index.php?8377]. | |||
** I would like to contribute to the mapping package, specifically the implementations of functions missing in Coordinates, Geodesy, Projections and | |||
* '''Rough time estimates:''' | * '''Rough time estimates:''' | ||
* For Mapping Package: | * For Mapping Package: | ||
Line 59: | Line 57: | ||
** Week 10 to Week 12 (July 30 to August 18): Write tests and Documentation. Code clean up and finalization. End of GSOC. | ** Week 10 to Week 12 (July 30 to August 18): Write tests and Documentation. Code clean up and finalization. End of GSOC. | ||
** After GSOC: Maintenance of Mapping Package in Octave Forge. | ** After GSOC: Maintenance of Mapping Package in Octave Forge. | ||
I have planned a 25 to 30 hour work schedule for every week. | I have planned a 25 to 30 hour work schedule for every week. | ||