**Week 11 to Week 12 (August 6 to August 18): This is a buffer time of two weeks to accommodate for any unpredictable delay. Refine tests and documentation for whole project. Code clean up and finalization. End of GSOC. | **Week 11 to Week 12 (August 6 to August 18): This is a buffer time of two weeks to accommodate for any unpredictable delay. Refine tests and documentation for whole project. Code clean up and finalization. End of GSOC. | ||
**After GSOC: Maintenance and further development of Mapping Package in Octave Forge. | **After GSOC: Maintenance and further development of Mapping Package in Octave Forge. | ||
* '''Detailed Schedule:''' | * '''Detailed Schedule:''' spreadsheet: [https://docs.google.com/spreadsheet/ccc?key=0AopkixSrywUIdE5aMngyYk53bEkxd2FtYUthS2hjbXc&usp=sharing] | ||