== Y: Your task ==
*I would like to work on '''implementing the 1D solver for boundary value problems'''
*A rough timeline for my project is the following:
Spending time before the official starting date perfecting any theoretical gaps surrounding the algorithms involved and their implementations
'''May 19-June22'''
Start working on the improvement of bvp4c solver.Create necessary unit tests and debugging.The goal for the midterm evaluation is a fully functional and
well documented version of the solver for octave.
'''June 23-June 27'''
Midterm evaluation period.Final tests and debugging for the bvp4c solver.
'''June 28-August 11'''
The first week will include a planning and design of the bvp5c solver for Octave.Matlab compatibility will be a target throught the planning process.
The coding will take approximately 1-2 weeks and then all the testing can begin.The goal for the final evaluation would be a robust and efficient
implementation of the solvers coming with the appropriate documentation.
*My only commitment during this period is my university exams,which take place during the last week of July.However I will be able to code around 4-5 hours a day,when not studying.